The “great lake” of Alvechurch returned in June, to the dismay of parish councillors who had been warning the temporary fix to the railway car park was a waste of money.
This picture (above) was taken by parish chairman Andy Humphries after what he described as “a few days of summer rain on dry ground.”
He added: “It will be interesting to see how long the lake takes to drain away, but we now know it will return to the same extent as before.”
The water was still standing in the car park as The Village went to press five days after the picture was taken.
This was despite Network Rail carrying out a “low budget” attempt to stop the pooling of water, having claimed the estimated cost of £500,000 to bring the car park up to standard, as required under the planning consent to upgrade the station, was “unaffordable”.
Village residents living nearby suffer when the car park is flooded because commuters park on roads surrounding the station.
Meanwhile, Network Rail has at least started to remove some of the ugly, and possibly hazardous, concrete blocks left along Station Road from the upgrade works.
* Barnt Green parish councillors have expressed frustration with Network Rail over the Cofton railway footpath closure.
Chairman Robert Cholmondeley said the council had been “fobbed off” and that there was no reason for the crossing to remain shut at present because the new train timetable will not come into effect until December 2017.