Blackwell and Barnt Green residents are facing several more months of travel disruption thanks to delays in Network Rail’s electrification project.
Project sponsor Richard Dugdale broke the news at Lickey & Blackwell’s Annual Assembly, when villagers were given the chance to have their say on issues affecting the parish.
Linthurst Newtown, which has been closed since January 10 while the railway bridge is raised to accommodate a new electrification system, was initially meant to reopen on March 30.
“The work is taking longer than planned, partly due to freight trains being diverted over this route after the Harbury earthslip blocked the Banbury-Leamington line, and also strong winds prevented the crane operation.” said Mr Dugdale.
Linthurst Newtown opened temporarily over the weekend of April 17, but has now been closed again until May 21.
During that weekend, Blackwell Road was closed while work on the bridge there was completed – this road will not now need to close again.
Hewell Lane, also closed since January 10, should have reopened on April 20, but the contractors have experienced problems with a water main running through the site and there has been a delay with the stone facing for the bridge.
Mr Dugdale told The Village that it could now be as late as July before that road can reopen.
He reported that there had also been delays with the improvements to Bromsgrove station – the 12-day railway closure scheduled for November this year will now be postponed into 2016, although the new timetable will still start in December as planned.
Blackwell residents were also keen to know if any decision had been made on the “yellow brick road” foot crossing from Fairways Drive to Blackwell Golf Course.
Mr Dugdale reiterated that Network Rail does not have the power to close it: “There will have to be a public consultation, with all views taken into account so that we can find a realistic solution.”
He added that a site meeting between Network Rail and county council representatives was “pending”.
At the parish council meeting before the public forum, Coun Janet King reported that a large number of residents had written to the council with their views, many in favour of keeping the crossing open.
She said the comments had been passed on to Mr Dugdale.