The following is an abridged report by Ron Brown of the Marlbrook Landfill Monitoring Group meeting in January to keep readers up to date with work at the tip:
Materials to be delivered to site:
The total authorised quantity of materials to comply with the application is 468,369 cubic metres. On the 5th May 2010 the balance was 33,360 cubic metres.
November 2010 – 16,560 cubic metres
January 2011 – 9,000 cubic metres
Note: No interpretation of these figures to indicate a final date of completion is possible since the flow rate of materials can not be assumed. The flow of lorries to the site will continue until all authorised materials have been delivered to the site.
Routing of lorries:
The routing of lorries to site is subject to an agreement between Bromsgrove District Council Planning Dept and the owners of the site, but it is not enforceable.
The site owners have, in the past, banned drivers from delivering to their site following verified complaints that lorries en route to their site have not used the agreed route.
‘Talk’ of a completion date:
As far as a completion date is concerned, the Monitoring Group has never pressed the owners of the site for a completion date simply because it would never be given.
The Group understand the reasons why that is so. There are at least three types of material to be imported and they need to be available when the work on the site demands them; the global recession has seen cutbacks to major works thus reducing availability.
There are also the restrictions placed by adverse weather conditions. It is not always possible to use much of the material as soon as it is delivered to site because it needs to be layered.
That means stockpiling, and it is these piles of material that give the impression that the levels are getting higher.
Landscaping:
The landscaping of the site and the construction of the golf course which began back in early 2010 continues. A point to note is that the current skyline as seen from Old Birmingham Road and Alvechurch Highway is distorted because of the stockpiling of materials.
Golf Course Club House:
Re-submission of the application is yet to be made. The completion of both course and club house is open ended.